8.7 Commissioning of Coke Cutter
8.7.1 The commissioning of coke cutter shall meet the following requirements:
1 Allow the coke cutter to move upward/downward at a low speed,adjust the travel limit switch according to the design documents.
2 Allow the coke cutter to move upward/downward in working speed for at least 2h,the operation shall be stable,the limit switch shall operate flexibly and reliably.
3 The tip-over of coke cutter at upper bending track shall be flexible and smooth for returning,the tip-over angle shall meet the requirements in the design documents.
Check method:observe,measure and check the commissioning records.