DL/T5210.3-2009电力建设施工质量验收及评价规程第3部分:汽轮发电机组(英文版)
上QQ阅读APP看本书,新人免费读10天
设备和账号都新为新人

Foreword

The standard series DL/T 5210"Code for Construction Quality Acceptance and Evaluation of Electric Power Construct"consists of 9 parts:

——DL/T 5210.1 Part 1:Civil Work

——DL/T 5210.2 Part 2:Boiler Unit

——DL/T 5210.3 Part 3:Turbine Generator Unit

——DL/T 5210.4 Part 4:Instrumentation and Control

——DL/T 5210.5 Part 5:Piping & System

——DL/T 5210.6 Part 6:The Equipment and the system with the Water Treatment and Hydrogen Generation

——DL/T 5210.7 Part 7:Welding

——DL/T 5210.8 Part 8:Processing Preparation

This Part is the third part of DL/T 5210.

This Part is formulated by the National Development and Reform Commission according to the requirements of the document"Announcement on Issuing the Professional Standard Project Planning in 2008"(Fagaiban Gongye〔2008〕No.1242).

During the drafting procedure,this Part references the content of"Standard for Quality Inspection and Evaluation of Thermal Power Construction—Turbine generator unit"(Dianzong[1998]No.145).

Appendix A,Appendix B in this Part are informative.

AppendixC,Appendix D in this Part are normative.

This Part is proposed by the China Electricity Council.

The Technical Committee for Standardization of Thermal Power Construction in power industry has the jurisdiction of and in charge of the explanation of this Part.

Chief drafting organizations:Zhejiang Thermal Power Construction Company and Jiangsu Electric Power No.3 Construction Engineering Company.

Participating organizations:Hebei No.1 Electric Power Construction Company Hunan Thermal Power Construction Company,Shandong Electric Power Construction Company Company,Shanxi No.4 Electric Power Construction Company.

Chief drafting staffs:Lu Huanhao,Yu Xingmei,Wang Weimin,Fan Youlin,Cheng Xinyu,Zhu Junmao,Yu Xiaoming,Yang Xiaoming,Xu Yunquan,Guo Zhenying,Liu Xinmin,Li Wei,Zhang Xinmin.

The former"Standard for Quality Inspection and Evaluation of Thermal Power Construction—Turbine generator unit"(Dianzong〔1998〕No.145)shall be abolished on the issuing date of this Part.

During the process of implementing this Part,the relevant opinions and advice,whenever necessary,can be posted or passed on to the Standardization Center of the China Electricity Council(No.1,Baiguang Road Ertiao,Beijing 100761).

English translators:Jiang Hong,Chen Yanfang,Meng Lixue

Chief reviewers:Chen Yanchun,Guo Rui,Wang Hongliang