上QQ阅读APP看本书,新人免费读10天
设备和账号都新为新人
6.2 Piping Layout for Hydrogen Service
6.2.1 The piping for hydrogen service should be routed above ground.
6.2.2 The piping for hydrogen service shall be weld joined;however,flanged joint may be used when the piping is connected to equipment or valves.
6.2.3 The piping for wet hydrogen service shall have a slope not less than 0.003,and drain shall be provided at low point of the piping.
6.2.4 Flame arrestor in hydrogen vent piping shall be located close to vent end.